Jun 7, 2019 1 min Steel frame & crane A crane will be onsite from the week beginning 17th June 2019. This will be for the erection of a steel frame building that will take 2...
Jun 7, 2019 1 min Basement works The basement works at Sergison Cottage have been completed. The retaining wall has been monitored throughout the process and checked by...
Dec 19, 2018 1 min Concrete Pour There will be multiple deliveries of concrete and a large extension arm onsite on Weds - Fri to facilitate pouring concrete.