Jun 7, 20191 minSteel frame & craneA crane will be onsite from the week beginning 17th June 2019. This will be for the erection of a steel frame building that will take 2...
Jun 7, 20191 minBasement worksThe basement works at Sergison Cottage have been completed. The retaining wall has been monitored throughout the process and checked by...
Dec 19, 20181 minConcrete PourThere will be multiple deliveries of concrete and a large extension arm onsite on Weds - Fri to facilitate pouring concrete.